M. LACHIA SETTY AND SONS LTD. V. THE COFFEE BOARD, BANGALORE INSC 197; AIR 1981 SC 162; 1981 SCR 884; 1980 SCC 636

From Advocatespedia
Revision as of 23:35, 2 July 2024 by 8247521077305041206345 (talk | contribs) (Supreme Court Of India Cases)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

As regards the alleged delay in holding the re-sale it must be observed that both the trial court as well as the High Court have taken the view that the same was held within reasonable time at the next "pool auction" conducted in the normal course. The results of the concerned "pool auction" were declared some time after 2 P.M. on October 8, 1952. The period of 17 days (14 days initial period plus 3 days of grace for taking delivery) expired on October 26, 1952, but the evidence on record shows that there was a general request on behalf of the successful bidders for extension of time for making payment and taking delivery and such extension had been granted by the Board upto November 10, 1952 by issuing a circular. We have already held that there was no valid retraction of bids by the appellants and to their knowledge their retraction had been rejected by the Board on October 8, 1952 itself. That the appellants were interested in the extension granted by the Board becomes evident from their telegram dated October 22, 1952 (Ex. A -129) seeking confirmation of the extension. After November 10, 1952. some reasonable notice of re-sale would have to be issued, so the defaulted coffee could not be put up for sale in the pool auction that was held in the month of November, 1952. The next pool auction was to be held in December, 1952 and, therefore, after issuing notice of re-sale on December 18, 1952 the re-sale was held by conducting a pool auction on December 23, 1952. In our view, both the Courts were right in taking the view that the re-sale had been held within the reasonable time.

Since all the contentions urged by counsel for the appellants have failed, the appeals are dismissed with costs.